Manager | Track Your Team's Progress and Workload

There are two statistics screens: one for each project and one for all projects. This article shows how to read both, and the three metrics that matter most.

There are two statistics screens: one for each project and one for all projects. This article shows how to read both, and the three metrics that matter most.

Statistics for a single project

Project › Statistics
Project › Statistics

Open the project and go to the Statistics tab. The four cards at the top: Completed tasks · Incomplete tasks · Overdue tasks · Total tasks.

  • Incomplete tasks by group — a horizontal bar for each step in the workflow. The step that swells up is the one that's bottlenecked.
  • All tasks by completion status — a donut chart of Completed / Incomplete.
  • Trend over time — choose Last 30 · 90 · 365 days and view three lines: Total tasks, Completed tasks, and Completed late.

A note on reading this: the four top cards cover the entire project, while the Trend over time block only covers the date range you select. It's normal for these two areas not to match; it's not an error.

Statistics across all projects

Tasks › Statistics
Tasks › Statistics

Click Statistics in the module's left column. This screen aggregates data from every project you participate in, with the same 30/90/365-day filter, and below it lists each project with a ratio in the form n/m tasks.

Current limitation: this screen states "The custom chart builder is still pending: the saved dashboard list endpoint rejected every parameter set tried; backend confirmation needed." This means you can't build your own charts yet. The message also makes clear that the built-in metrics are real data — use them as normal.

Three metrics worth tracking weekly

MetricWhere to find itThreshold for action
Overdue tasksThe third card in Project statisticsOver 10% of total tasks — hold a review meeting right away
The most swollen stepIncomplete by groupOne step holds more than half of the open tasks
Completed lateThe red line in Trend over timeAn upward trend three weeks in a row

Balance workload across team members

Tanca doesn't yet have a prebuilt per-person workload screen. Here's what you can do right now:

  1. Go to the project's List tab.
  2. In the Task group filter, change the grouping to assignee.
  3. Read the number of open tasks for each person in each group's heading.
  4. Combine this with the Time to complete entered on each task (article B10-05) to estimate hours, not just count tasks — ten small tasks are lighter than two large ones.

If your company needs per-person workload reports at scale, raise it with the Tanca product team. This is a known gap.